PMP试题解析(第十章 项目沟通管理)
单选题(每题1分,共2道题)
1、 [单选]沟通对项目成功非常关键,作为项目经理,你有3个相关方需要沟通。这时候又加进来一位新相关方也需要沟通,沟通渠道增加了几条?Communication is key to the success of a project. As the project manager, you had three stakeholders with whom you needed to communicate. A new stakeholder has been added with whom you also need to communicate. How many communication channels have been added?
A:3
B:4
C:6
D:10
正确答案:B你的答案:B
解析:原来3个相关方加上项目经理是 4 个人,沟通渠道 C 24=N*(N-1)/2=(4*3)/2=6 条;新增 1 人变成 5 个人沟通,C 25=N*(N-1)/2=(5*4)/2=10 条;沟通渠道新增:C 25- C 24=10-6=4 条。
2、 [单选]项目实施过程中,开发阶段的工作已经外包给一支海外团队。执行项目期间,海外团队通知说有关于开发的重要信息有遗漏,但国内设计团队说已经提供了所有设计文档。造成这种情况最有可能的原因是什么?In an implementation project, the development phase has been outsourced to an off-shore team. During the execution of the project, the off-shore team states that vital information to proceed in the development is missing. However, the on-shore design team has stated that all design documents have been provided. What could most likely be the cause of this situation?
A:未正确创建沟通管理计划failed to create communication management plan correctly.
B:未正确创建相关方参与计划 failed to create stakeholders’ engagement plan correctly.
C:项目经理缺乏沟通技巧 the project manager lacks communication skills.
D:未正确创建风险管理计划failed to create the risk management plan correctly.
正确答案:A你的答案:A
解析:沟通管理计划应明确定义团队之间沟通的方式、频率,确认的方式和时限等,确保沟通的及时性和有效性。见10.1.3.1。