PMP每日一题

2021-06-16  本文已影响0人  键盘小蟲
  1. Project manager A realizes that additional resources are required to complete their project on time and asks project manager B for assistance with resources. If project manager B agrees, what document should be reviewed?
    项目经理A认识到需要额外资源来按时完成项目,并请求项目经理B提供资源方面的协助。如果项目经理B同意,应审查哪一份文件?

参考答案:B。
解析:资源日历显示每种资源的可用工作日和工作班次。

2.While working on an assembly line, a team member reports the high failure rate of a product.
What should the project manager use to support this evidence?
在装配线上工作时,一名团队成员报告了产品的高失败率。项目经理应使用什么来支持这项证据?

参考答案:C。
解析:质量测量指标专用于描述项目或产品属性,以及控制质量过程将如何验证符合程度。

3.For a system implementation project in country A, a manager completes the deliverables defined in the scope and customer accepts them. This system was successfully implemented in several other countries, but the users in country A are dissatisfied with some of the functions.
What should the project manger do next to close the Project?
对于一个在A国的系统实施项目,项目经理完成了范围中定义的可交付成果,且获得客户验收。系统之前已成功在多个其它国家实施,但是A国的用户对某些功能不满意。
收尾项目时,项目经理下一步应该怎么做?

参考答案:C。
解析:可交付成果已经获得客户验收,说明项目完成技术收尾;但是用户对某些功能不太满意,在行政收尾时应该总结经验教训、了解用户不满意的原因、项目团队今后应该怎么做等等,更新在组织过程资产中,供未来项目使用。

  1. A project team is working on the scope baseline component of the project management plan.
    What document should be included?
    项目团队正在努力确定项目管理计划范围基准组成部分。应将哪份文件包含在内?

参考答案:A。
解析:范围基准包括了范围说明书、WBS、WBS词典。

  1. The following are the project tasks:
    Task A (duration 4 days);
    Task B (duration 3 days);
    Task C (duration 4 days);
    Task D (duration 2 days);
    Task E (duration 3 days);
    Task F (duration 4 days).
    Tasks D and F cannot start until task C is complete. Tasks A and B can start any time after task
    C starts, but must complete before the end of the project. Task E cannot start until task D is
    complete. During the execution of task B, Which was started one day after task C had started, An
    exception happened which will cause a 2-day delay for this task.
    What action should be taken to ensure the project is completed on time?
    项目任务如下:
    任务A(持续时间4 天);
    任务B(持续时间3 天);
    任务C(持续时间4 天);
    任务D(持续时间2 天);
    任务E(持续时间3 天);
    任务F(持续时间4 天)。
    任务D 和任务F 只能在任务C 结束后开始。任务A 和任务B 可以在任务C 开始后的任何时间内开始,但是必须在项目结束前完成。任务E 只能在任务D 完成后开始。任务B 是在任务C 开始一天后才开始的,在执行任务B 过程中,发生了一件例外事项,导致该任务延期2 天。

参考答案:D。
解析:首先根据题意,画出进度网络图,可知任务B在非关键路径上,1+3=4,延期2天变为6天,对项目没影响。

更多pmp练习题,关注小程序【PMP全真模拟】~