eero first visit to CEI

2017-09-14  本文已影响0人  MrBao_cd6a

Justin Chien/Andy

Jay Kruse

Siamak

Quality Habib

1.Compal presentation first

VINCENT complaint KSP2 layout not ready

2. Interview section from Andy

- interface with EPM and organization ?

- who will in charge of NPI material management?  VL answer: TPE PJE in charge in NPI, PUR place PO, PUR will take over from PVT

- what's the next step after BOM fixed? Aaron answered

- what's the PVT quality target, Vec, PVT SMT 99%, FATP 98%

- If yield is poor as 94%, how to confirm and action to PM, VL PM daily report and safe launch report

- What's the action if op didn't follow SOP, Stephen: re-training, and PE team check if any reasonable inside need engineering team help

- How to test non battery products? VL dummy battery