the following was my work today.
1.this morning I trained the operators on assembly process how to write the first part inspection record. especially to check the hole for install warning lines and the process line. however,the production supervisor suggested me to add these two items in packaging first part inspection record,so i updated it.
2.confirmed the rust of E&O materials from india and contacted relevant departments to deal with them for order.
3.to deal with the problem of xld’s shim didn't match the backplate.